The Klamath
Project encompasses an alternately barren and wooded area of
The Klamath
Project covers territory in
Settlers carved their niche
in
To protect the
I'm a raw recruit with a brand new suit.
One hundred dollars bounty.
And I've just come down to
To fight for
The First Oregon paid the
cavalry troopers $31 to $39 a month. Sergeants received a few dollars more.
Looking for a strategic
location to secure major migration routes, the Regiment's officers chose the
Five years later conflicts
between the Klamath and Modoc Indians, placed on the same lands by the United
States Government, resulted in the Modoc War. Kientpoos, more commonly known as
Captain Jack, led the Modocs to
In 1882, five
years after the Modoc War, farmers introduced irrigation to the Klamath area.
Several Linkville residents incorporated the Linkville Water Ditch Company. They
dug a low capacity ditch connecting town lots to the
The Van Brimmer
Brothers also started a small ditch in 1882, to irrigate 4,000 acres near the
Oregon-California border on
In October 1903, John T.
Whistler, Oregon District Engineer of the Reclamation Service, investigated the
Klamath region at the request of Chief Engineer, later Reclamation Director,
Fredrick H. Newell. Whistler recommended a controlling dam at the lower end of
Approval of the Klamath
Project rested on adjudication of all vested and conflicting water rights;
surrender of rights on Lower Klamath and Tule Lakes; cessation of rights and
title to the federal government by Oregon and California for Lower Klamath and
Tule Lakes; and Congressional approval allowing Hitchcock to destroy
navigability of the two lakes. Hitchcock and Newell received petitions for a
Reclamation project beginning in late 1904 and early 1905, as residents of
Only the Klamath Canal
Company threatened project authorization. Three men named Hawkins, Brown, and
Gould incorporated the Klamath Canal Co. on
Reclamation filed on the
waters of
The Justice Department
responded by issuing a temporary restraining order. Meanwhile land owners in the
Local farmers unanimously
supported the project and organized the Klamath Water Users' Association on
The Klamath Project
incorporated several privately built canals and, Reclamation initially
constructed Clear Lake Dam and Reservoir, Lost River Diversion Dam, and the A
(Main), B (East Branch), and C (South Branch) Canals on the Project.
The
Construction of the Klamath
Project started under the direction of Project Engineer D. W.. Murphy in 1906,
and continued under Walter W. Patch, his 1909, replacement. Mason, Davis &
Company of
Mason, Davis & Co. could not
work on three miles of the
The rain and snow, of winter,
made canal excavation a slow and arduous task. The work required three steam
pumps to handle water from the canal. Mason and Davis could only use the horse
teams on the upper portions of the canal cut. The company received a contract
extension and completed two sections of the canal
Reclamation invited bids for
construction of the
Original plans intended the
Another board of engineers,
consisting of Henny, Hopson, and Murphy, convened in
The plan went awry as only
one company bid on the schedules. Reclamation considered the bid excessive and
decided to proceed by force account for the entire canal. Work started in June
1907. Excavation work promptly ran into unexpected dilemmas. The hillside slopes
of the canal location proved very steep, with houses and orchards immediately
below the site, and a power plant and wooden pressure pipe nearby, on the
The Project History
complained of having scarce and unsatisfactory laborers, whom Reclamation paid
$3.00 for an eight hour day, for several months. Reclamation finished the canal
excavation in October 1908. Upon priming the canal, Reclamation discovered
considerable seepage which caused movement of the lower banks. Reclamation lined
the right bank and bottom of the canal, with four inches of concrete, for a
distance of 267 feet. Workers placed riprap the same distance along the left
bank. The lining and riprap reduced the seepage greatly, but Reclamation
maintained a force of three to five men for several months to puddle subsequent
seepage with soil and manure.
Reclamation awarded the
contract for three schedules of the South Branch Canal to Maney Brothers of
Saint Louis on May 8, 1908, and they began work five days later. Maney Brothers
did all the excavation work with horses and scrapers. Reclamation allowed a
contract extension from
The
W. H. Mason of
J. M. Heizer conducted
studies of the proposed
Reclamation placed William
Sargeant in charge of dam construction. In April 1909, he supervised building of
the construction camp, organizing the work, and receiving equipment and
supplies. Austrians, Montenegrins, and Serbians formed the majority of the work
force. Reportedly the Austrians proved outstanding workers, though supervisors
considered all satisfactory. Reclamation bought $10,000 worth of new equipment
for construction, and had to haul the new equipment fifty-five miles, from the
railroad to the dam site. The Reclamation Service increased the labor force in
June to begin work on the waste channel. Workers used material excavated from
the waste channel in the rockfill portion of the dam.
The outlet conduit from the
dam to the waste channel stretched 156 feet when completed. The outlet started
as two chambers near the foot of the dam, controlled by cast iron gates. The
chambers joined forty feet below the gates, forming the main conduit. Workers
excavated an average of eighteen feet deep. They encountered porous lava
covering hard basalt ten feet deep. Under the basalt they found "a sticky, red,
volcanic mud." The crews excavated cutoff trenches through the muck to the hard
rock three feet below and filled them with concrete to stabilize the foundation.
The conduit is ten feet in diameter.
Reclamation used levees built
by Jesse Carr to divert Willow Creek into
Workers used material
excavated from the waste channel for the rockfill. The arrangement limited the
placement rate on the fill to the excavation rate of the channel. Reclamation
built
Reclamation crews dug through
two feet of tule and marsh grass across the channel to the foundation of the
earth embankment. After draining water from the site, the ground surface became
impenetrable to the orange-peel excavator acquired for clearing the site.
Workers used a plow on the hard material. The material immediately beneath the
surface proved too soft to support loaded wagons. Workers rigged up a hoisting
engine at one end of the site, attached a plow and slip to it with a cable, and
used the combination to excavate the soft material.
Seven feet below the surface
lay solid basalt slabs with only a few seams. Crews washed the rock, then
cleaned the cracks with wire and grouted them. Work crews discovered lava blocks
separated by clay seams forming the foundation on the east side of the river.
They used gads, steel wedges used to break out loose pieces of rock, and bar
drills, small rock drills, to excavate the trench between the lava boulders,
afterwards filling the seams with grout or cement, depending on the size of the
cracks. On the west side, porous lava seams permeated the foundation. Workers
excavated through the lava to the solid rock below. They filled the excavated
portions with concrete. A four ton, cast iron roller leveled and compressed the
re-fill to four inch layers.
Crews filled gaps in the
rockfill at the contact point with the earth embankment for a proper foundation.
They placed the earth, taken from the east slope of the valley, in six inch
layers, watered it, and compressed it with a four ton roller. A nearby borrow
pit supplied the stones for the riprap on the upstream slope.
Lava encountered in
excavation of the waste channel varied in hardness, causing problems for
Reclamation crews. They used 40 percent dynamite to "spring" drill holes, then
finished blasting with 50 to 500 pounds of "Champion" powder. Where water in the
excavation site prevented the use of powder, the crews used only the dynamite.
Uncertainty of the rock's density often resulted in charges being too light or
too heavy. Explosions from light charges dissipated through seams and soft
spots. Heavy charges dislodged more material than desired. The resulting
excavated material ranged from powdered rock to boulders. The boulders required
block-holing, or drilling holes in the rocks for a small charge of explosives to
break them for removal.
Labor shortages afflicted
construction of
Reclamation identified two
saddles to the south of
The labor shortages at
Reclamation intended to build
President William Howard
Taft authorized the issuance of bonds against the Reclamation Fund in 1910, for
future work on projects including the Klamath Project. Before expenditure of
money from the bonds, he ordered a Board of Engineers from the Army Corps of
Engineers examine and report on each project using the bonds. The Board of
Engineers visited the Klamath Project September 30 through
Reclamation engineers
decided, in 1910, to put Lost River Diversion Dam at a site called
Though it still required some
finishing work, Reclamation began storing water behind the Lost River Dam in
January 1912. The gatekeeper and a small work force applied the final touches.
They built two wing walls at the downstream end of the dam, a garage near the
dam, and completed other smaller projects. The Lost River Diversion Dam is a
hollow U shaped multiple arch weir, with straight embankment wings. The dam's
crest length extends 675 feet with a structural height of 42 feet.
W. H. Mason of
Mason waited for the arrival
of an excavator to continue canal excavation. The machine arrived in June 1911,
but a poor design limited its effectiveness. After moving only 2,000 cubic
yards, Mason discarded the excavator in favor of team work. Mason lost valuable
time, and Reclamation lost patience. In September 1911 Reclamation suspended the
contract schedules contract not yet started by Mason, and completed them by
force account, finishing
James Jory contracted one
schedule on the diversion channel and began in May 1911. Jory started with a
small force and repeatedly experienced delays. He made little headway by the end
of the year. By March 1912, Jory realized he faced penalties if work did not
make the deadline. Jory pushed his work through continuing winter conditions and
financial losses, completing the contract on
Construction remained light
for the next several years. Reclamation built a sixty-four foot truss span by
force account, in 1912, to extend the
Reclamation received
authorization to excavate the
Reclamation finished the
Reclamation drew up plans for
the
Reclamation reached an
agreement on
Payne listened to arguments
and explanations about the contract in a hearing on
Construction of the Lower
Lost River Diversion Dam coincided with construction of the J Canal, to supply
water to the Tule Lake Division. W. D.. Miller of
Excavation of J Canal by
force account began
Reclamation built Malone
Diversion Dam, on the upper
Lava bedrock comprised the
foundation on the south side of the river bed. On the north side lay lava
boulders and gravel mixed with clay, ash, and cinders. A "black mucky material,"
of decomposing vegetation, covered the bed to a depth of about six feet. Workers
removed the material with a stiff leg derrick down to the foundation material.
Slip scrapers and laborers' hands took care of the rest. Reclamation started
placing the earthen embankment
Concrete placement started
Reclamation experienced labor
shortages in the 1920s, as it had in previous years on the project. The Service
experienced a high turnover rate during construction of Malone Dam. Common labor
received between $3.60 and $4.50 a day. Reclamation paid carpenters $7.00 a day
on the dam construction. Wages in the surrounding area reached $4.00 to $5.00 a
day for common labor. Malone Diversion Dam consists of a concrete gate structure
with a height of 32 feet, and a crest length stretching 515 feet.
Reclamation opened bids for
twelve miles of the
W. E. McAboy received a
contract to build the checks and wasteway structures on the
W. D. Miller received the
contract to build the Gerber Dam, located on Miller Creek; formerly the Horsefly
site, on
Gerber Dam is a concrete
medium thick arch, 460 feet long at its crest. The dam stands eighty four and
one-half feet high with a top width of five feet and a maximum base width of
twenty-four feet. The spillway consists of an uncontrolled overflow section at
the dam's center. Water first spilled in 1958. Gerber Reservoir has a total
capacity of 94,300 acre-feet.
Reclamation built the
New construction on the Tule
Lake Division began in 1940 with the creation of the Modoc Unit of the division.
Reclamation started excavation on the P and P-1 Canals
Reclamation awarded the
contract for the Tule Lake Tunnel to J. A. Terteling & Sons. The tunnel drained
water from the
Terteling lined the tunnel
with a layer of concrete, measuring a maximum of seven inches and minimum three
inches thick. Workers used a pumpcrete machine to inject the concrete into the
tunnel forms. Terteling's concreting equipment often failed, due to its age, but
the company finished the work on
John Gardner of
In the early 1940s,
Reclamation instituted plans to convert lands reclaimed from the
Squirrels caused major
problems for the Klamath Project early in its history. Squirrel holes in canal
embankments caused eleven of twelve breaks in A and C Canals in 1915.
Fortunately only three breaks proved serious; two in A Canal and one in C Canal.
Reclamation officials deemed the original timber lining in C Canal unsafe in
1919. Reclamation re-lined the canal with concrete starting in fall of 1919, and
continuing into 1920. During freezing weather, workers covered the concrete work
with canvas and heated it with fires to prevent damage. Working from
Once again labor shortages
hindered Reclamation's progress. Regulations limited the maximum wage paid by
Reclamation to $4.50 per day. Elsewhere employers paid laborers $5.00.
Reclamation received the authority to pay $5.00 per day, and by the end of 1920,
workers on C Canal received $5.50-$6.00 per day. Carpenters received $8.00 per
day. Reclamation now deducted $.50 per meal from the workers' pay. Wages
continued to fluctuate in 1921 and 1922. Wages dropped to $3.60 per day in 1921,
and fell to $3.00-$3.20 in early 1922. Common laborers' pay rose to $4.00 per
day on
Reclamation advanced from
simply lining C Canal to enlarging it. Work crews used an excavator on softer
material, but they encountered a layer of hardpan strata requiring heavy
blasting. The Oregon State Highway Department undermined the
Reclamation lined two
sections of A Canal with a two inch layer of Gunite in 1927. On the first
schedule, they lined 400 feet of the left bank and 600 feet of the right bank.
The lining stretched 1,600 feet on the second schedule. Reclamation deepened the
CCC recruits on the project
concentrated on maintenance and rodent control. Shortly after moving into the
Klamath region, CCC enlistees excavated a small drain in A Canal to facilitate
the removal of sediment. In 1936, they paved the canal with concrete and rocks.
Reclamation worked on enlargement of J Canal from February 3 to
Reclamation added three foot
high flashboard supports to Clear Lake Dam's spillway in 1938, increasing the
reservoir's capacity by about 60,000 acre-feet. The CCC raised
On
The outbreak of World War II
brought many changes to the Klamath Project. Reclamation placed armed guards at
major project facilities. Army engineers began inspecting possible sites for a
relocation camp on the Klamath Project March 28, 1942. They located a site at
Tule Lake, near Newell, California, and the War Relocation Authority (WRA)
started construction on April 18 of the same year. Construction of sufficient
housing for 10,000 Japanese finished on May 31, 1942, and the WRA started
increasing camp facilities to house 6,000 more.
The Interior Department
signed an agreement with WRA Director Dillon Myer on June 22, 1942, giving the
WRA 800 acres of Klamath Project land for the relocation camp and another 35,000
acres for agricultural production. An agreement the following December 14, added
683 acres to the camp site and 1,845 acres for agriculture. Construction of the
Tule Lake Relocation Camp affected work on the Klamath Project, because it drew
off all available labor and once again raised wages.
The WRA announced on July 23,
1943, it would segregate and house all "disloyal" Japanese evacuees at the Tule
Lake camp. On November 5, 1943, disturbances at the Tule Lake camp occurred. In
response, the Army took over operation of the camp. The Navy announced the
takeover of the Klamath Falls airport on October 28, 1943. Reclamation employed
about thirty German prisoners of war on the project for removing moss and some
maintenance work. In 1945, Japanese-American evacuees lined .86 miles of the M
canal running through Tule Lake camp.
The N-16 lateral in the Tule
Lake Division received a pre-fabricated asphalt lining in 1949. High winds
during placement operations, damaged the lining in a narrow section of the
lateral. Reclamation suspected the section was the source of excessive seepage
during testing, so the engineers segregated the section. However, in tests, the
wide section lost more water, through seepage, than the narrow section.
Engineers determined lower water levels reduced the amount of seepage.
Gerber Dam began showing
seepage in its horizontal and vertical construction joints in early 1951,
apparently caused by improper cleanup of the joints during construction.
Engineers recommended a liquid neoprene (synthetic rubber) lining to seal the
joints. Reclamation scheduled repairs to start on October 1, 1951, when Gerber
Reservoir reached its lowest point, with 25.4 feet of the dam exposed. Crews
chipped out the disintegrated concrete, wider on the inside than outside, and
put new concrete in. They brushed the neoprene over the seams, extending it six
inches on either side of the joints.
Secretary of the Interior
Stewart L. Udall approved a contract with Pacific Power and Light Company
(California-Oregon Power) for development of the Keno Canal in June 1967. In May
1970, the Tulelake Irrigation District held a public dedication changing the
name of the Lower Lost River Diversion Dam. They renamed it the Anderson-Rose
Dam in honor of the founders of the irrigation district; Sam Anderson and Ivan
Rose.
The Klamath Water Users'
Association (KWUA) ratified the contract with the Department of the Interior on
November 3, 1905. Original estimates placed the cost of the project to water
users at $20 a month. In 1908, Reclamation announced it would charge the water
users $30 per month, but the water users denied liability for the extra $10. On
January 25, 1909, Secretary of the Interior Richard A. Ballinger ordered
construction on the Klamath Project suspended. The KWUA gave in, agreeing to pay
the additional charge, and construction resumed.
The Klamath Project attracted
people of varying national origins to work on farms or the project. The
Project History of 1913, recorded three families each of Russians and Swiss
moved onto project lands. Many farmers found themselves hard pressed to make
payments on their bills. A group of Russian families, living near Lost River
Dam, left after selling in 1916; not able to keep pace with their expenses.
Despite such financial difficulties J. B. Bond; the Project Manager in 1917,
remained optimistic. He wrote, "The procedure of foreclosing mortgaged property
under the project is becoming unknown, and it is a safe prediction that it will
soon be spoken of as `a lost art'."
Potential farmers also
remained optimistic. In a public drawing during the spring of 1917, 175 filed
for 42 tracts of land. Surrounding communities, especially Klamath Falls,
Oregon, grew along with the rural population (see Table I.). Merrill, Malin, and
Midland, the other project towns grew less rapidly, and in some cases decreased.
Construction of Malone Dam allowed the irrigation of 6,040 acres of the Langell
Valley Division's west side, and 4,532 near Bonanza, Oregon, making that town of
300 part of the project. The Horsefly and Langell Valley Irrigation Districts
formed by 1925, and the Sunnyside Irrigation District in 1926. The Malin and
Shasta View Pumping Districts formed about the same time, and 8,000 acres of
their land received water from the enlargement of the Adams Canal. Klamath Falls
reached a population of 10,000 people in 1926.
Reclamation opened land entries in the Klamath Project, to World War I veterans, between November 1922 and January 27, 1923. Afterward, Reclamation opened the entries to any applicants. Secretary of the Interior Hubert Work issued Public Order no. 19 in 1927, opening 145 farm units in the Tule Lake Division. Klamath Falls had a population of 15,000 by the end of the decade. The project's farm population grew to 2,833 by 1934.
Table I.
Klamath Project Populations, 1918, 1922, and 1946.
City |
Year |
Population |
|
Klamath Falls |
1918 |
5,000 |
|
|
1922 |
7,000 |
|
|
1946 |
30,951 |
|
Bonanza |
1946 |
262 |
|
Malin |
1918 |
100 |
|
|
1922 |
200 |
|
|
1946 |
570 |
|
Merrill |
1918 |
600 |
|
|
1922 |
500 |
|
|
1946 |
-- |
|
Tulelake |
1946 |
915 |
|
Project Farms |
1918 |
1,480 |
|
|
1922 |
1,300 |
|
|
1946 |
860 |
Source: Reclamation, Project History, Klamath Project, 1918, 141;
Reclamation, Project History, Klamath Project, 1922, 199; Reclamation,
Project History, Klamath Project, 1946, 140
Klamath Falls boomed with the
advent of World War II, reaching 25,968 people in 1945, but the farm population
dropped 2,812 people from 1934. Klamath Falls started declining by 1950, though
the other project towns continued to increase. The farm population reached 4,255
in 1951. The Klamath Project's population declined more heavily in the late
twentieth century. The farm population fell to 1,825 by 1979. Klamath Falls
retained only 17,737 of its boom population by 1990. Merrill, Malin, Bonanza,
and Tulelake had a combined population of 2,862 in the 1990 census. Midland did
not even appear.
Reclamation regained control
of relocation center lands in 1946, including Tulelake. During the same year the
Bureau opened land entries to veterans returning from World War II. Surplus farm
equipment and abandoned barracks buildings greatly aided in the veterans'
settlement. Reclamation separated the barracks into smaller structures, and the
buildings provided temporary housing for the new settlers. The veteran settlers
on Klamath included Eleanor Jane Bolesta, a former WAVE who became the first
woman homesteader on a Reclamation project. Bolesta's husband, Charles, a Marine
during the war; received debilitating wounds while fighting on Guam.
The Klamath Project primarily
supplied irrigation water for local agriculture. The project irrigates over
200,000 acres on about 1,400 farms. Farms on the project grow a wide variety of
crops (see Table II.). Forage crops for livestock comprised the majority grown
in the early years of the project. Early reports showed alfalfa lands valued at
twenty to thirty dollars an acre at the time of Klamath's authorization. By
1910, the value increased to $50 an acre, rising to $100 by 1912.
Potatoes moved up in value on
the Main Division during the 1920s. Acreage devoted to potatoes increased by
almost 600 from 1925-26. The monetary return increased from $127,254 to $266,850
during the same year. At the same time alfalfa yields on the Tule Lake Division
increased by 20 percent. The project further supports a large livestock
business. Cattle, sheep, and hogs comprise most of the project's livestock.
The Klamath Project provides
many activities for people interested in water sports and outdoor recreation.
The area is ripe for swimming, boating, water skiing, camping, and hunting. The
Fish and Wildlife Service operates recreational facilities at Lower and Upper
Klamath, and Tule Lakes. The Fish and Wildlife Service manages the Clear Lake
National Wildlife Refuge which includes Clear Lake Reservoir. The Bureau of Land
Management administrates the facilities at Gerber Reservoir. Reclamation
operates facilities at Malone Dam.
Reclamation established
experimental farms in the marsh lands near Lower Klamath Lake in 1912. They
drained water from the marsh and attempted to reclaim the land. The tule in the
marsh became difficult to till after it dried, limiting Reclamation to one acre
of land on the farm. Reclamation tried to grow a variety of crops on the farms,
but many died. Grains and grasses survived, but did not reach normal growth. The
Army Board of Engineers, of 1910, reported the experimental farms were not
self-supporting, and operated at the expense of project farmers. The Army
recommended the Department of Agriculture assume control. Reclamation turned the
farms over to the Klamath County Agriculturalist in 1914.
Events on the
Klamath Project mirrored events in the western United States. The project
witnessed labor fluctuations and home front activities during war. The agreement
between Reclamation and California-Oregon Power, leading to construction of the
Link River Dam, created an unusual circumstance in Reclamation projects. A power
company building and operating a dam on a project, did not often occur. Most
important the Klamath Project participated in the ongoing quest for water,
indigenous to the American west, and answered the increasing demand for
irrigation. Facilities on the Klamath Project continue to provide a large
population with a variety of services.
Eric A. Stene was born in
Denver, Colorado, July 17, 1965. He received his Bachelor of Science in History
from Weber State College in Ogden, Utah, in 1988. Stene received his Master of
Arts in History from Utah State University in Logan, in 1994, with an emphasis
in Western U.S. History. Stene's thesis is entitled The African American
Community of Ogden, Utah: 1910-1950.
Bibliography
Manuscripts
and Archival Collections
Record Group 115. Department of the Interior. Bureau of Reclamation Records. National Archives and Records Administration, Denver office.
Annual Project History, Klamath Project: 1912-15, 1917-30, 1934-43, 1945-46, 1950-51, 1959-60, 1979.
Operation and Maintenance Report, Klamath Project, 1916.
Project Reports.
"Report on the Seepage Test of the Experimental Buried Prefabricated Asphalt Membrane Lining Test Section in the N-16 Lateral of the Klamath Project." Compiled by Brooks O. Custer. Edited by Mark D. Taylor, Jr., January 1951. Box 473.
"Report on Repair of Gerber Dam with Neoprene Membrane." Box 473.
Government
Documents
Department of Commerce. Bureau of the Census. Twenty-First Census of the United States, 1990: Population and Housing. Bureau of the Census, 1990, on CD-ROM.
Water and Power Resources Service. Project Data. Denver: Government Printing Office, 1981.
Books
Conrat, Marie and Richard. Executive Order 9066: The Internment of 110,000 Japanese Americans. California Historical Society: Sacramento/Los Angeles, 1972.
Gray, Edward. An Illustrated History of Early Northern Klamath County, Oregon. Bend, Oregon: Maverick, 1989.
Palmberg, Walter J. Copper Paladin: A Modoc Tragedy; A Story of the Two Principal Role-Players of the Modoc Indian War of 1872-73. Bryn Mawr, Pennsylvania: Dorrance & Co., 1982.
Stone, Buena Cobb. Fort Klamath: Frontier Post in Oregon; 1863-1890. Dallas: Royal Publishing, 1964.
Articles
Darr, A. L.. "Gerber Dam Construction, Klamath Project, Oregon." New Reclamation Era. December 1925, 182-84.
"Malone Diversion Dam Built." The Reclamation Record. August 1923, 285-86.
"Oregon-California Farms Open to Entry." The Reclamation Record. November 1922, 285.
Thomas, E. H.. " Livestock at the Klamath County Fair." The Reclamation Record. December 1921, 548-49.
Thye, Carl J. " The Bureau Reclaims Its Own." The Reclamation Era. April 1947, 90-92.
"Tule Lake Lands Opened to Veterans." The Reclamation Era. September 1946, 202.
"War Relocation Centers Acquired." The Reclamation Era. September 1946, 195.
Other
Parker, Sybil B., ed. McGraw-Hill Dictionary of Scientific and Technical Terms, 4th Edition. New York: McGraw-Hill, 1989